Nightmare From a Local Pole Building Contractor

Reader RICK in OOLTEWAH writes:
“Regrettably, after going with a local “pole building” contractor I find myself with a semi-completed building and a number of issues (I believe) to work through. The attached photos will hopefully help complete the picture. I was mostly ignorant of the pole building process, best practices, etc., instead just trusting the builder. I’m less ignorant now, thanks to your blog, but my timing could have been much better. I contracted to have a 30x40x12, to be used as a garage/machine shop, built on a leveled dirt pad, to be concreted later. After two months of waiting with said dirt pad ready, through several rainstorms, the contractor sent materials and a crew. They moved quickly, mostly getting the building up in a day. So quickly that no one noticed the standard trusses, not scissor as agreed upon. A 12′ overhead door (again stipulated) was not possible, and a 10’6″ went up in its place. This was a distraction until another hard rain showed water flow directly under the wall, highlighting what I think is the bigger issue. The splash plank has, in places, large gaps underneath (3-6″). By itself not so concerning, but for the fact there is no exposed splash plank on the exterior. The siding and edge trim is run to absolute bottom (nearly to grade). Meanwhile the doors float roughly 8 inches above grade/bottom edge of the trim/splash plank. This leaves a monstrous gap between the overhead when fully down and the highest the grade can go without backfilling against metal. Measurement inside shows exactly 12′ from the TOP of the splash plank to the bottom of the truss. They apparently zeroed out the build from the top of the plank, not the bottom, leaving the better part of 8 inches to make up for in the approach, fill and concrete, and a number of other areas. At this point the contractor has not called in a month, leaving off at “having a guy come install the cupola”. The silver lining for me thus far is I only have 1/3 of the money paid in. Given the way things have gone, I’m in no rush to give him any more, at least without being able to spell out what the problems and solutions are. I keep hoping Im still misunderstanding the process, and am seeing problems where there are none. But if that isn’t the case, what can be corrected and how?”

Mike the Pole Barn Guru says:
You are not alone, thousands of people, just like you, contract to have new buildings erected by “professional” building contractors, only to find what they thought they were getting and what they have received are two different animals. This is just one of many reasons why I encourage people to consider DIY instead – as an average physically able person who will read instructions often ends up with a much nicer finished product than what they would have paid for. If one lacks either time or ability to self-build, it is imperative to know fully what one has ordered and to literally camp out on site to verify work is done as agreed upon.
Hold on to your money tight until all issues are rectified. You do hold the ‘upper hand’ as your building has not been built as stipulated in your contract agreement – it does not have scissor trusses, nor a 12 foot tall overhead door. Rightfully, you could demand and it is likely a court would agree, for said building to be taken down and replaced with what you had ordered.
In order to reach a compromise solution, and provided you can get by with 11’3″ of height going through your overhead door, I would propose this:
Builder to add a 2×4 Pressure Preservative treated to UC-4A or better, below current splash plank.
Overhead door to be changed out to 11’3″ tall (as I can tell from your photos, it appears there is six inches from bottom of your building’s current splash plank to bottom of door).
Builder to fine grade interior to be even with bottom of newly installed treated 2×4.
Builder to grade exterior for 10 feet around building to slope at 5% from bottom of treated 2×4 outward away from building.
While this is not what you agreed upon, it may afford a practical solution to a nightmare you never should have had.
P.S. While crew is onsite, they should replace trim to right of your overhead door opening. Having a splice at this location is both unsightly and dangerous. They should also place a screw on both sides of every high rib of steel siding and roofing at both bottom and top ends of every panel (you will find this will then match manufacturer’s installation instructions).

One thing my client did need is a builder, he is a busy business professional and just does not have the time to do his own work. I did some quick research and came up with about a dozen builders in his area, who are willing to provide construction services for 50% of the cost of materials or less.
DEAR POLE BARN GURU: I have some serious issues with a pole barn I recently had built! I hired a general contractor to build it for me knowing it would be a little more expensive but that way if there was any issues it was his responsibility to deal with subcontractors. Well it’s been a nightmare ever since the sub he hired to construct it didn’t set the man door at the right height so when the concrete crew poured the floor they went off the bottom of the man door instead of the garage doors which is the proper way to do it. Well when they went to do the apron they discovered the siding was three inches below where the concrete had to be so they had to cut the wainscot three inches. I decided to start taking measurements! This is a 30×40 building and none of the posts are on center. They are anywhere from 16 inches off to 2 inches off center on an 8 foot span. The roof joists are supposed to be 4 foot span but they are all over the place too! Anyway he’s trying to tell this is ok it’s still structurally sound and I shouldn’t worry about it! Anyway you get the picture. He wants his money and I am refusing to give final payment till I get another contractor to look at it and give me a cost estimate to fix the problems his sub screwed up on. What’s your thoughts on the way I’m handling it? CONFOUNDED IN CABLE
Rick related to me this from the client:
“Who can build a good pole barn in this area? Looking to build a building and need someone that can build a sturdy pole barn.”
The obvious ones – are the tools to be able to effectively build. And they don’t come cheap, even if obtained second hand at pawn shops or sources like Craigslist. An efficient “work mobile”. All of the good tools on the planet are meaningless, if the crew can’t make it to the jobsite every day. And the work mobile doesn’t run for free. Last I looked, gasoline wasn’t a bargain and the price at the pump is just a small portion of what it costs to maintain a good vehicle.
Remember those hours the general contractor will save you on the jobsite? Plan on spending twice the amount of time to find a good general contractor. Do your due diligence and hire someone with excellent references and the professionalism to do what he was hired to do.